Tuesday, December 22, 2009
Wednesday 23rd December
Wednesday, December 2, 2009
Thursday 3rd December
Monday, November 30, 2009
Tuesday 1st December
Thursday, November 26, 2009
Friday 27th November
Wednesday, November 25, 2009
Thursday 26th November
Just the barge and capping to go.
Thursday we will have
Electricians
Plasterers
Carpenters
and Plumbers on site.
So, along Jacks' Corner Road you can expect
many Utes and trucks and maybe a delivery of the capping and barges
Hope this helps
Regards
Chris
christreuen@bigpond.com
Tuesday, November 24, 2009
Wednesday 25th November
Monday, November 23, 2009
Tuesday 24th November
Thursday, November 19, 2009
Friday 20th November
Wednesday, November 18, 2009
Thursday 19th November
If it didn't get to site yesterday expect it along the road today.
There will also be a large crane to lift the iron onto the roof.
The cladding carpenters will be on site.
The plumbers will be on site and
The electrician will be on site.
So , along Jack's Corner Road you can expect:
All the usual Utes and trucks and
The large truck with roofing iron and
The crane.
Hope this helps
Regards
Chris
Christreuen@bigpond.com
Thursday, November 12, 2009
Friday 13th November
Tuesday, November 10, 2009
Wednesday 11th November
Monday, November 9, 2009
Tuesday 10th November
Thursday, November 5, 2009
Friday 6th November
Weather permitting.
The carpenters will be on site and
The scaffolding guys are coming to raise the decks on the house scaffolding.
Thats about all I know.
So if the sun shines, along Jacks' Corner Road you can expect:
Various utes and trucks and the scaffolding truck.
Hope this helps
Regards
Chris
christreuen@bigpond.com
Wednesday, November 4, 2009
Thursday 5th November
Monday, November 2, 2009
Tuesday 3rd November
Thursday, October 29, 2009
Friday 30th October
Wednesday, October 28, 2009
Thursday 29th October
Tuesday, October 27, 2009
Wednesday 28th October
The carpenters think they are going to be there for the next six weeks. At least they are staying in the valley.
Wednesday is another day with just the carpenters on site. But the delivery that didn't turn up Tuesday should turn up on Wednesday.
So, along Jack's Corner Road you can expect:
The carpenters Utes and trucks and
a truck delivering the roofing material.
Hope this helps
Regards
Chris
christreuen@bigpond.com
Monday, October 26, 2009
Tuesday 27th October
Another not so busy day expected Tuesday.
The carpenters are back on site and there should be more deliveries of Roofing material.
I think the roofers themselves are not due until Wednesday.
So, along Jacks' Corner Road you can expect:
The carpenters utes and
The delivery truck with the roofing material.
Hope this helps
Regards
Chris
Christreuen@bigpond.com
Sunday, October 25, 2009
Monday 26th October
Thursday, October 22, 2009
Friday 23rd October
Friday it is plumbers and carpenters and that is about it.
So, along Jacks' Corner Road you can expect;
The carpenter's two utes and
The plumber's truck.
An easy day all round.
Hope this helps
Regards
Chris
christreuen@bigpond.com
Wednesday, October 21, 2009
Thursday 22nd October
Tuesday, October 20, 2009
Wednesday 21st October
Thursday, October 15, 2009
Friday 16th October
The carpenters will be back.
The electrician has taken a few days off as he just gets in the carpenters way.
The plumber has about two hours work to do and then he can take a week off.
Oh, And the guy is coming to do the flashing above the sill brick.
So it will be quiet along Jacks Corner Road, but you can expect.
The usual tradesman's utes and trucks
Hope this helps
Regards
Chris
Christreuen@bigpond.com
Wednesday, October 14, 2009
Thursday 15th October
Tuesday, October 13, 2009
Wednesday 13th October
I think it is going to be quiet on Wednesday.
The plumbers say they are ahead of schedule and want to go somewhere else.
The electrician says he is waiting for the carpenters to finish something. I secretly think he is moonlighting on another job.
The Carpenters will be back in force and that's about it except for a delivery that I know nothing about.
So, along Jack's Corner road, you can expect :
A few mealy carpenters utes and maybe
A delivery truck.
Hope this helps
Regards
Chris
Christreuen@bigpond.com
Monday, October 12, 2009
Tuesday 13th October
Weather permitting, I am expecting.
The carpenters to start the cladding.
The plumbers to finish the fire system.
The electrician to return. He seems to shrink away at the first sign of rain.
The bricklayers have finished which is shame because the were great guys.
And maybe deliveries of windows and wood.
So along Jack's Corner Road, you can expect.
Assorted utes and trucks and
Maybe some deliveries.
Hope this helps
Regards
Chris
christreuen@bigpond.com
Sunday, October 11, 2009
Monday 12 October
Bricklayers coming to finish.
Carpenters aplenty to finish the roof beams.
Electrician, there are miles of cables in this joint.
Plumbers, for the sprinkler system and maybe some deliveries.
So, along Jack's Corner Road you can expect.
Assorted utes and Trucks
Hope this helps
Regards
Chris
christreuen@bigpond.com
Thursday, October 8, 2009
Friday 9th October
The timber to finish the roof is due
And I think there are more bricks coming.
So along Jacks' Corner road you can expect:
The above utes and trucks for the various tradespeople
and delivery trucks for both the timber and the bricks.
Hope this helps
Regards
Chris
Christreuen@bigpond.com
Tuesday, October 6, 2009
Wednesday 7th October
Monday, October 5, 2009
Tuesday 6th October
The electrician will be on site.
The plumbers will be on site
The scaffolding guys will be on site.
The bricklayers will be back
and if I keep my fingers crossed maybe the carpenters will re appear.
I don't know of any deliveries due but maybe there is more scaffolding to come.
So , along Jack's Corner Road, if the weather doesn't interfere
you can expect.
All the associated utes and trucks.
Hope this helps
Regards
Chris
Thursday, October 1, 2009
Friday 2nd October
Wednesday, September 30, 2009
Thursday 1st October
The plumber is due first thing in the morning.
The electrician had a great time with someone else but will be back today.
Scaffolders are due back.
Deliveries of scaffolding, bricks and maybe weatherboards.
So, along Jack's Corner Road you can expect;
Tradesman's ute and trucks
Large truck delivering scaffolding and
Maybe a large truck delivering weatherboards.
Hope this helps
Regards
Chris
christreuen@bigpond.com
Tuesday, September 29, 2009
Wednesday 30th September
Brick layers are due back.
Plumber should be on site.
Electrician is being unfaithful and going to another job for a day.
And maybe the carpenetrs will be there.
There may be some deliveries of sand /cement/ bricks.
So, along Jack's Corner Road you can expect.
The above utes and trucks and maybe a delivery truck.
Hope this helps
Regards
Chris
Christreuen@bigpond.com
Monday, September 28, 2009
Tuesday 29th September
The plumbers are due on site.
The carpenters should be there.
The bricklayers will be back again and
The electrician will be there again.
All depending on the weather.
So along Jack's Corner Road you can expect
All their utes and trucks.
Hope this helps
Regards
Chris
Christreuen@bigpond.com
Friday, September 25, 2009
Saturday 26th September
Thursday, September 24, 2009
Friday 25th September
The bricklayers will be back again
The electrician will be on site.
The plumbers are due back again
and if the windows didn't show up Thursday
then they are still expected.
So, along Jack's Corner Road you can expect:
Bricklayer's Truck
Electrician's van
Plumber's truck and ute and
maybe the delivery trucks.
Hope this helps
Regards
Chris
Christreuen@bigpond.com
Wednesday, September 23, 2009
Thursday 24th September
Thursday, September 17, 2009
Friday 18th September
Hope this helps
Regards
Chris
Wednesday, September 16, 2009
Thursday 17th September
There are also a number of deliveries due.
So, you can expect along Jack's Corner Road.
The carpenters truck and ute.
The bricklayers trucks.
A truck delivering bricks.
A truck delivering tiles.
The electrician's van
and maybe the plumbers truck.
Hope this helps
Regards
Chris
Monday, September 14, 2009
Tuesday 15th September
The crane is due back to place more of the roof trusses.
The carpenters are due back.
The plumber is supposed to be on site with his crew
The electrician is back on site
The site manager is organising some steel work on site.
and the bobcat is due back to fill in some more trenches.
So, along Jack's Corner road you can expect.
The crane
The carpenter's truck and utes
The plumber's truck and ute
The electrician's Van
and the truck with the bobcat on the back.
Sorry for the inconvienence but
hope this helps
Regards
Chris
Christreuen@bigpond.com
Thursday, September 10, 2009
Friday 11th September
Busy time while I was away and the house is looking great.
The pool is in and it is full steam ahead.
On Friday they will be placing the roof trusses and this will take a few days.
So , you can expect along Jack's Corner Road.
The carpenter's trucks and utes
an a crane to lift the trusses into place.
Hope this Helps
Regards
Chris
christreuen@bigpond.com
Wednesday, August 26, 2009
Thursday 27th August
Tuesday, August 25, 2009
Wednesday 26th August
The pool has been postponed till next week and not much else happened at Noggarah.
Wednesday we are expecting the carpenters back on site and possibly more deliveries of wood.
So, along Jack's Corner Road you can expect:
The carpenter's Truck and utes
And possibly a truck delivering wood.
Hope this helps
Regards
Chris
Christreuen@bigpond.com
Monday, August 24, 2009
Tuesday 25th August
The carpenters had a great day today and nearly got the frame up.
Tuesday should be fairly quiet.
The carpenters are having the day at another job.
The pool is due to be delivered around 9-9.30 in the morning.
The truck with bobcat will be coming in earlier and so will the pool installation guy.
So along Jack's Corner Road you can expect;
The truck with bobcat on board
The pool guy's ute
and the truck delivering the pool.
Hope this helps
Regards
Chris
Christreuen@bigpond.com
Sunday, August 23, 2009
Monday 24th August
I think it is going to look like a fire station.
A fairly quiet day is expected for Monday.
The Carpenters are due and so is another delivery of windows.
The electrician is coming down to check that all is going OK
And the site manager will be there to set everything straight.
And the load of sand may also be delivered.
So along Jack's Corner Road you can expect:
Tradesman's utes and truck.
Large truck delivering windows and
Maybe a truck and dog delivering sand.
Hope this helps
Regards
Chris
Christreuen@bigpond.com
Thursday, August 20, 2009
Friday 21 August
Wednesday, August 19, 2009
Thursday 19th August
The carpenters are starting on Thursday.
The pool digging will continue and there is still a possibility
that the windows will be delivered Thursday or Friday.
So, along Jack's Corner Road you can expect:
Peter the site manager in his ute
Two carpenter's utes and a small truck.
The boys utes coming to do more pool digging and
Maybe the window truck.
Hope this helps
Regards
Chris
Christreuen@bigpond.com
Tuesday, August 18, 2009
Wednesday 19th August
Wednesday we start the digging the pool.
And the carpenters are turning up to start erecting the frame.
I am not expecting the delivery of the pool till Friday but that has not been confirmed as yet.
There may also be a delivery of sand for under the pool.
So along Jack's Corner Road you can expect:
The truck with the small excavator on it.
The carpenters in their utes.
Possibly the truck and dog with the sand.
And Dave Selby to oversee everything.
Hope this helps
Regards
Chris
Christreuen@bigpond.com
Monday, August 17, 2009
Tuesday 18th August
So, the last of the frames have arrived. And I ain't got a one yet.
The carpenters are either starting Tuesday or Wednesday and the plumber may be on site Tuesday to continue the drainage work.
I am not expecting any big deliveries on Tuesday but the windows and pool are due later in the week.
So, along Jack's Corner road we may have:
The carpenter's Ute and
The plumber's Truck.
Hope this helps
Regards
Chris
Christreuen@bigpond.com
Sunday, August 16, 2009
Monday 17th August
Sorry, I have just found out that we are having a delivery tomorrow.
And I thought Monday was going to be a day of rest.
Monday , the remainder of the frames are going to be delivered.
So, along Jack's Corner Road you can expect:
One huge 40" semi trailor fully laden with the frames for the shed.
Hope this helps
Regards
Chris
Christreuen@bigpond.com
Thursday, August 13, 2009
Friday 14th August
Thank you so much for your patience yesterday. It was a tough day with a lot of concrete trucks.
The concretors did an amazing job and managed to finish the entire main slab in one day. Mind you it was after 5pm when they signed off.
Friday is supposed to be an easy day.
The electrician will be back connecting the power to the main house site and
There is a possibility that the frames for the garage may be delivered today.
So along Jack's Corner Road you can expect;
The electrician's ute and
Maybe a 40" semi-trailer with frames on it.
Hope this helps
Regards
Chris
Christreuen@bigpond.com
Wednesday, August 12, 2009
Thursday 13th August
So, weather permitting, Thursday we pour the slab.
It could be a very busy day as this slab is about twice the size of any other pour we have done.
The good news is that this will be the end of the concrete trucks for a while.
So along Jack's Corner road On Thursday you can expect:
The concrete crews arriving early in the morning and
a huge number of concrete trucks from about 7.30am till around 2 0r 3pm
I hope this helps
Regards
Chris
christreuen@bigpond.com
Tuesday, August 11, 2009
Wednesday 12th August
Monday, August 10, 2009
Tuesday 11th August
Hi Tom,
These guys are doing a great job but believe it or not we still need another delivery of pods and steel Tuesday.
The concretors will continue to prepare the main slab.
The electrician will be getting the power across to the main house.
The plumber will be doing storm water and sewerage to both sites
And the excavator will be doing a lot of trenching.
So along Jack's Corner Road you can expect;
Tradesman's utes and trucks
The truck with the excavator on the back.
The delivery truck with the pods and steel and
The council inspector to make sure we are doing everything correctly.
Hope this helps,
Tom, lovely to have you on board
Regards
Chris
Christreuen@bigpond.com
Sunday, August 9, 2009
Monday 10th August
Monday should be a fairly easy day.
The concrete crew are back and
there should be another shipments of Pods arriving.
So along Jack's Corner Road you can expect:
Tradesman's utes and Trucks and
A large truck and trailor delivering the pods
Hope this helps
regards
Chris
Christreuen@bigpond.com
Thursday, August 6, 2009
Friday 7th August
Friday will be busy.
We are pouring the two wings of the house and this pour is bigger than last wednesday.
The concrete crew will be there first thing in the morning and then the trucks should start arriving.
So, Please take care along Jack's Corner Road as there will be:
Tradesmans Utes
And concrete trucks aplenty.
Again, some of these trucks will be impassable as oncoming traffic on some sections of the road.
So, I thank you for your consideration and patience in advance.
Hope this all helps
Regards
Chris
Christreuen@bigpond.com
Wednesday, August 5, 2009
Thursday 6th August
At this stage Thursday should be a fairly quiet day and then another pour on Friday.
So on Thursday there will be the concreting crew preparing part of the house slab and
The electrician will be there in the afternoon.
I also expect the pest treatment guy will be there in the afternoon and
The council inspector will also be on site in the afternoon.
I am not expecting any major deliveries today.
I hope Wednesday was not too difficult for you all. But I must say I found the truck drivers really courteous on the roads.
So along Jack's Corner Road you can expect:
Mainly tradesman's utes
Hope this helps
Regards
Chris
Christreuen@bigpond.com
Tuesday, August 4, 2009
Wednesday 5th August
Monday, August 3, 2009
Tuesday 4th August
The plan is for the first pour to happen on wednesday if there are no hiccups.
So along Jacks Corner Road you can expect:
The concrete crew in their truck.
The plumber in his truck.
The electrician in his ute
And maybe another delivery of Waffle Pods and steel.
Hope this helps
Regards
Chris
Christreuen@bigpond.com
Sunday, August 2, 2009
Monday 3rd August
The rest of the steel should arrive.
The waffle pods are due to arrive.
The crew to prepare the slab is supposed to be here first thing in the morning.
The small excavator is going to be deepening some trenches.
The plumbers is doing some more drainage.
And the electrician will be on site.
So along Jack's Corner Road you can expect.
Tradesman's utes
and large trucks a plenty.
Hope this helps
Regards
Chris
Christreuen@bigpond.com
Friday, July 31, 2009
Saturday 1st August
The rain water tank guys are coming to pick up their formwork.
And only half of the steel was delivered so they may be delivering the rest either today or monday.
So along Jack's Corner Road you can expect:
Tradesman's utes
Truck to collect the formwork
and maybe a truck delivering steel.
Hope this helps
Regards
Chris
Christreuen@bigpond.com
Thursday, July 30, 2009
Friday 31st July
If all goes well the 2nd shipment will come in on Friday and possibly another shipment on Friday afternoon or Saturday Morning.
The concretors will be in and there will also be large delivery trucks for the waffle pods and the steel for the slab.
The plumbers are due back to finish some drainage and the electrician will be doing some finishing touches.
So please take care on Jacks Corner Road tomorrow as there will be:
Tradesman's utes a plenty.
Large semi trailers
Delivery trucks.
Some of these trucks may be impassable on sections of the road so could you please either pull into a driveway or reverse back to a passable location.
If you see trucks waiting at the entrance to Griffins Fire trail this may mean that they are waiting for a truck to come up the hill. Please feel free to ask the driver if it is safe to proceed.
Hope this helps and
sorry for the inconvienence.
Chris
Christreuen@bigpond.com
Wednesday, July 29, 2009
Thursday 30th July
Another fairly quiet day at Noggarah on Thursday.
The electrician will be there and maybe a gravel delivery.
And there is a possibility that the first of the frames will be arriving.
So along Jack's Corner Road you can expect:
Tradesman's utes
and maybe a truck and dog
And maybe the truck with frames
Hope this helps
Regards
Chris
Christreuen@bigpond.com

Tuesday, July 28, 2009
wednesday 29th July
Monday, July 27, 2009
Tuesday 28th July
Sunday, July 26, 2009
Monday 27th July
The slab is going to look like a porcupine when it is finally laid.
Monday, weather permitting could be a busy day.
The electrian wants to check all the ducting before the concretors get to it.
The plumber still needs to finish some minor stuff before the steel goes in.
The bobcat has some more filling in to do.
And the concretors are arriving to lay the steel.
So if it is a fine day, along Jack's Corner road you can expect
Tradesman's utes a plenty.
Truck carrying the re enforcing steel.
A truck and dog with gravel.
I hope this helps
Regards
Chris
Christreuen@bigpond.com
Friday, July 24, 2009
Saturday 24th July
That will be the only thing.
No deliveries expected.
So along Jack's Corner Road you can expect.
Tradesman's utes and me in a panic.
Hope this helps
Regards
Chris
Christreuen@bigpond.com
Thursday, July 23, 2009
Friday 24th July
Weather permitting both the plumber and the electrician will be working.
There will be some plumbing delivery in the morning and around midday
the bobcat will be coming back on site to do a clean up.
Also there will be two deliveries of gravel by truck and dog.
So along Jack's Corner Road you can expect
Tradesman's utes
Small deliver trucks
The truck and dog with the gravel
and the truck carrying the bobcat.
Hope this helps
Regards
Chris
Christreuen@bigpond.com
Wednesday, July 22, 2009
Thursday 23rd July
The plumbers have finished the internal drainage.
The septic tanks have arrived.
The tennis court is nearly finished.
But we continue on with the airconditioning.
So along Jack's Corner Road you can expect:
Tradesman's utes
and some small deliveries.
Hope this helps
Regards
Chris
Christreuen@bigpond.com
Tuesday, July 21, 2009
Wednesday 22nd July
and Wednesday we should be doing:
More Plumbing work
More work on the electricals and
I am told the septic system is turning up
So along Jack's Corner road You can expect:
Tradesman's utes
and the truck delivering the septic System.
There may also be some minor deliveries.
Hope this helps
Regards
Chris
Christreuen@bigpond.com
Monday, July 20, 2009
Tuesday 20th July
And Tuesday shouldn't be too bad either.
The plumber will be working at noggarah,
The electrician will be working there
The bobcat will be doing a bit of work around the place.
And the tennis court fencers will be there to finish off.
They may be moving the small excavator off site.
So along Jacks Corner Road you can expect;
Tradesman's utes
Maybe plumbers deliveries
Truck moving the excavator out
And maybe the truck with the septic tanks
Hope this helps
Regards
Chris
Christreuen@bigpond.com
Sunday, July 19, 2009
Monday 20th July
The plumbers will be on site
and
the electrician will be working on site today.
If the tennis court guys have finished their job at Goulbourn then I am expecting them
to start on the fencing today.
I expect there will be a delivery of gravel in a truck and dog.
And a slight possibility that that the remaining septic tanks will be delivered.
So along Jack's corner road you can expect:
Tradesman's utes with trailors
A truck and dog
and maybe the septic tanks.
Hope this helps
Regards
Chris
Christreuen@bigpond.com
Friday, July 17, 2009
Friday 17th July
I was expecting:
The tennis court guys to do the fencing.
The delivery of the septic tanks
The plumber and electrician to continue works under the slab.
The large excavator to be moved out today
And there is a site meeting with the concretors
So Along Jack's Corner Road we can expect :
Tradesman's Utes
Delevery truck for the septic system
and a large truck moving the excavator
Hope this helps
Regards
Chris
Christreuen@bigpond.com
Wednesday, July 15, 2009
Thursday 16th July
Tuesday, July 14, 2009
Wednesday 15th July
Weather Permiting;
The tennis court guys are coming to lay the grass and there will be a large sand delivery for them around 11am.
The plumber and his team will be there for the day and I expect that there will be a delivery for them.
The electricain and his off sider will be there for the day.
And the trenching team will be working all day on the site.
So definately tradesmans truck and some deliveries on Jack's Corner Road tomorrow.
Hope this helps
Regards
Chris
Christreuen@bigpond.com
Monday, July 13, 2009
Tuesday 14th July
There may be some sand and gravel deliveries.
And some deliveries for the plumber.
More trenching and pipe work to be done.
So, On Jack's Corner Road you can expect:
Tradesman's trucks
And some delivery trucks.
Hope this helps
Regards
Chris
Chris.treuen@bigpond.com
Sunday, July 12, 2009
Monday 13th July