Wednesday, August 12, 2009

Thursday 13th August

After a few adjustments the engineer has signed off on the preparation of the main slab.

So, weather permitting, Thursday we pour the slab.

It could be a very busy day as this slab is about twice the size of any other pour we have done.
The good news is that this will be the end of the concrete trucks for a while.

So along Jack's Corner road On Thursday you can expect:

The concrete crews arriving early in the morning and

a huge number of concrete trucks from about 7.30am till around 2 0r 3pm

I hope this helps
Regards
Chris