Wednesday, August 5, 2009

Thursday 6th August

A big day on Wednesday but the pouring of the slab went well.

At this stage Thursday should be a fairly quiet day and then another pour on Friday.

So on Thursday there will be the concreting crew preparing part of the house slab and

The electrician will be there in the afternoon.

I also expect the pest treatment guy will be there in the afternoon and

The council inspector will also be on site in the afternoon.

I am not expecting any major deliveries today.

I hope Wednesday was not too difficult for you all. But I must say I found the truck drivers really courteous on the roads.

So along Jack's Corner Road you can expect:

Mainly tradesman's utes

Hope this helps
Regards
Chris